We have listed below some timescales for the separate phases that are involved with Self Building. You must remember, however, that the times listed are only a guide as individual Architects/Designers, Planning Depts, Builders and Tradesmen in different areas will work at their own pace. When making initial enquiries you should ask for an indication of "How long it will take" to do the work and if necessary incorporate it into any contract.

Locating land1 month to several years (average 3 - 4 months)
Designer/Architectural work 1 to 3 months
Planning Building Control 2 to 4 months (but can take longer)
Building process6 to 8 months if you have a single contractor or if you are self managing your contractors.

If you are intending to DIY a large amount of the work, it then is totally dependent on the amount of time you allocate to the project. Timber frame houses are often chosen for the reason that they are simple and quick to erect the main shell.